Client
Imperial College Healthcare NHS Trust

Project Name
Oncology Outpatients Department – Hammersmith Hospital

Duration
27 Weeks

Value
£1,551,000

Key Storm Site Team
Paul Firth – Contracts Manager
Ryan Flannery – Project Quantity Surveyor
Pat Finn – Site Manager

Quantity Surveyor:
Mortimer Isaacs LLP

Architect:
Ansell + Bailey

Mechanical Engineer:
RSP

DescriptionDownload PDF version

This project involved the refurbishment of the Oncology department at Imperial college healthcare trust at Hammersmith Hospital. Although the building was unoccupied, this hospital is a busy environment so upmost care and consideration of the surrounding area was taken.

Complexities with the scope of works included:

  • Live hospital Environment
  • Programme
  • Mechanical and Electrical

How were these mitigated?

  • Storm effectively communicated with the Architects & Trust to deliver the works within programme.
  • Our Site management team was present for all structural elements on the project as well as overseeing the M&E installation process.
  • Working around a live hospital is second nature to Storm as we consistently work in these projects.

How did Storm add value?

  • Storm added value to this project through its extensive experience running sites in live environments, through utilising our experience working on complex hospital sites we were able to Keep a hospital running with minimal disruption to the hospitals operations.

Testimonial
Our Oncology Outpatients scheme was the first project awarded to Storm Building at Imperial Healthcare NHS Trust and we are delighted with the vibrant and stylish new unit. The quality of workmanship is excellent and Storm’s ability to work collaboratively with us was particularly useful with mitigating some tricky backlog maintenance issues uncovered along the way and when managing the impact of the works with surrounding clinical areas.

Christopher Knight BA(Hons) MSc APMP,
Senior Estates Project Manager
Imperial College